On May 30, 2026, during first shift at approximately 6:25 AM, Operator Sarah Jones and Maintenance Technician Mike Smith responded to repeated carton jams on Filler 2 after a guide rail loosened because two mounting bolts had backed out. Operator Sarah Jones observed that the guide rail was visibly shifting during operation, heard cartons striking the rail before jamming, and found the mounting bolts loose during inspection. The rail was realigned and the fasteners were replaced, restoring production after 41 minutes. Approximately 3,600 bottles of production were lost. The issue occurred twice that month, so the team upgraded the washer to a more secure split lock washer. Sarah added the improvement to her CIL and informed her supervisor. Mike updated the next PM to check the split lock washer and verify its effectiveness.